Fishermans Bend
Innovation Project
June 2025 to December 2026
Fishermans Bend, Victoria
Winslow Infrastructure
Scope of works
- Mechanical soil screening of excavated site material to remove asbestos containing material and inert waste
- Soil screening to obtain a clearance by an independent hygienist to allow Winslow on-site reuse of material
- Soil screening to obtain a clearance by an independent hygienist to for disposal of the material free of asbestos containing material
- Loading, cartage and disposal by EPA registered carriers and vehicles of contaminated material to a licenced landfill facility for treatment and safe burial
- All works are completed under asbestos removal conditions per WorkSafe Victoria’s regulations and requirements
Volumes
- Approx. 60,000m3 of material successfully processed and remediated
- Approx. 55,000 tonnes of material successfully disposed of at a licenced landfill facility
Challenges
- All remediation works have been completed in close proximity to the public with appropriate asbestos removal controls put in place to mitigate risk of exposure
- Tight area for access with large machinery and large stockpiles in the remediation zone
- Traffic and time on road travelling to and from the licenced landfill facility