Fishermans Bend

Innovation Project

June 2025 to December 2026

Fishermans Bend, Victoria

Winslow Infrastructure

Scope of works

  • Mechanical soil screening of excavated site material to remove asbestos containing material and inert waste
  • Soil screening to obtain a clearance by an independent hygienist to allow Winslow on-site reuse of material
  • Soil screening to obtain a clearance by an independent hygienist to for disposal of the material free of asbestos containing material
  • Loading, cartage and disposal by EPA registered carriers and vehicles of contaminated material to a licenced landfill facility for treatment and safe burial
  • All works are completed under asbestos removal conditions per WorkSafe Victoria’s regulations and requirements

Volumes

  • Approx. 60,000m3 of material successfully processed and remediated
  • Approx. 55,000 tonnes of material successfully disposed of at a licenced landfill facility

Challenges

  • All remediation works have been completed in close proximity to the public with appropriate asbestos removal controls put in place to mitigate risk of exposure
  • Tight area for access with large machinery and large stockpiles in the remediation zone
  • Traffic and time on road travelling to and from the licenced landfill facility